Which of the following is the most accurate definition of a project risk?
Gary is the project manager for his organization. He is working with the project stakeholders on the project requirements and how risks may affect their project. One of the stakeholders is confused about what constitutes risks in the project. Which of the following is the most accurate definition of a project risk?
Which one of the following is NOT an output of the risk response planning?
You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?
Which of the following acts promote a risk-based policy for cost effective security?
Which of the following acts promote a risk-based policy for cost effective security? Each correct answer represents a part of the solution. Choose all that apply.
Which of the following refers to an information security document that is used in the United States Department
Which of the following refers to an information security document that is used in the United States Department of Defense (DoD) to describe and accredit networks and systems?
which one of the following is an output of risk monitoring and control?
You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
which of the following is likely to increase?
You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders’ approval, to fast track the project work to get the project done faster. When you fast track the project which of the following is likely to increase?
What positive risk response has happened in this instance?
Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is more than $125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric’s relationship with the vendor. What positive risk response has happened in this instance?
What risk response has management asked Harry to implement?
Harry is the project manager of the MMQ Construction Project. In this project Harry has identified a supplier who can create stained glass windows for 1,000 window units in the construction project. The supplier is an artist who works by himself, but creates windows for several companies throughout the United States. Management reviews the proposal to use this supplier and while they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units in time for the project’s deadline. Management asked Harry to find a supplier who will guarantee the completion of the windows by the needed date in the schedule. What risk response has management asked Harry to implement?
Which one of the following is a valid risk response for a negative risk event?
There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?
Which of the following statements correctly describes DIACAP residual risk?
Which of the following statements correctly describes DIACAP residual risk?