what in project management?
Harry is a project manager of a software development project. In the early stages of
planning, he and the stakeholders operated with the belief that the software they were
developing would work with their organization’s current computer operating system. Now
that the project team has started developing the software it has become apparent that the
software will not work with nearly half of the organization’s computer operating systems.
The incorrect belief Harry had in the software compatibility is an example of what in project
management?
Which of the following statements about Discretionary Access Control List (DACL) is true?
Which of the following statements about Discretionary Access Control List (DACL) is true?
Which types of project tends to have more well-understood risks?
Which types of project tends to have more well-understood risks?
Which of the following processes is described in the statement below?
Which of the following processes is described in the statement below? “This is the process
of numerically analyzing the effect of identified risks on overall project objectives.”
Is Eric’s organization liable to pay the ZAS Corporation for the work they have completed so far on the
Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to
complete part of the project work for Eric’s organization. Due to a change request the ZAS
Corporation is no longer needed on the project even though they have completed nearly all
of the project work. Is Eric’s organization liable to pay the ZAS Corporation for the work they
have completed so far on the project?
which one?
Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key
project stakeholders have completed a round of qualitative risk analysis. He needs to
update the risk register with his findings so that he can communicate the risk results to the
project stakeholders – including management. Mark will need to update all of the following
information except for which one?
Federal Government information security standards?
Numerous information security standards promote good security practices and define
frameworks or systems to structure the analysis and design for managing information
security controls. Which of the following are the U.S. Federal Government information
security standards? Each correct answer represents a complete solution. Choose all that
apply.
Which of the following tasks are identified by the Plan of Action and Milestones document?
Which of the following tasks are identified by the Plan of Action and Milestones document?
Each correct answer represents a complete solution. Choose all that apply.
What should Jenny do with these risk events?
Jenny is the project manager for the NBT projects. She is working with the project team and
several subject matter experts to perform the quantitative risk analysis process. During this
process she and the project team uncover several risks events that were not previously
identified. What should Jenny do with these risk events?