What is the project’s schedule performance index?
You are the project manager of the NNH Project. In this project you have created a
contingency response that the schedule performance index should be less than 0.93. The
NHH Project has a budget at completion of $945,000 and is 45 percent complete though the
project should be 49 percent complete. The project has spent $455,897 to reach the 45
percent complete milestone. What is the project’s schedule performance index?
Which of the following Internet laws has the credit card issuing company violated?
A Web-based credit card company had collected financial and personal details of Mark
before issuing him a credit card. The company has now provided Mark’s financial and
personal details to another company. Which of the following Internet laws has the credit
card issuing company violated?
Which of the following is a 1996 United States federal law, designed to improve the way the federal government
Which of the following is a 1996 United States federal law, designed to improve the way the
federal government acquires, uses, and disposes information technology?
what quantitative risk analysis will review?
Gary is the project manager for his project. He and the project team have completed the
qualitative risk analysis process and are about to enter the quantitative risk analysis process
when Mary, the project sponsor, wants to know what quantitative risk analysis will review.
Which of the following statements best defines what quantitative risk analysis will review?
Which of the following is used to indicate that the software has met a defined quality level and is ready for
Which of the following is used to indicate that the software has met a defined quality level
and is ready for mass distribution either by electronic means or by physical media?
What approach can Amy take to create a bias against risks that will affect the schedule of the project?
Amy is the project manager for her company. In her current project the organization has a
very low tolerance for risk events that will affect the project schedule. Management has
asked Amy to consider the affect of all the risks on the project schedule. What approach can
Amy take to create a bias against risks that will affect the schedule of the project?
Which of the following processes is a structured approach to transitioning individuals, teams, and organizatio
Which of the following processes is a structured approach to transitioning individuals,
teams, and organizations from a current state to a desired future state?
Where will you record the mitigation response?
You are the project manager for your company and a new change request has been
approved for your project. This change request, however, has introduced several new risks
to the project. You have communicated these risk events and the project stakeholders
understand the possible effects these risks could have on your project. You elect to create a
mitigation response for the identified risk events. Where will you record the mitigation
response?
Which of the following RMF phases is known as risk analysis?
Which of the following RMF phases is known as risk analysis?
What will Jenny reply to you?
Jenny is the project manager of the NHJ Project for her company. She has identified several
positive risk events within the project and she thinks these events can save the project time
and money. You, a new team member wants to know that how many risk responses are
available for a positive risk event. What will Jenny reply to you?