which could cause delays in subsequent work beginning. This is an example of what type of risk event?

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?

How many months will you need to use the solution to pay for the internal solution in comparison to the vendor

You are the project manager for your organization. You have identified a risk event that your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor’s solution?


Page 8 of 43« First...678910...203040...Last »