what quantitative risk analysis will review?

Gary is the project manager for his project. He and the project team have completed the
qualitative risk analysis process and are about to enter the quantitative risk analysis process
when Mary, the project sponsor, wants to know what quantitative risk analysis will review.
Which of the following statements best defines what quantitative risk analysis will review?

What approach can Amy take to create a bias against risks that will affect the schedule of the project?

Amy is the project manager for her company. In her current project the organization has a
very low tolerance for risk events that will affect the project schedule. Management has
asked Amy to consider the affect of all the risks on the project schedule. What approach can
Amy take to create a bias against risks that will affect the schedule of the project?

Where will you record the mitigation response?

You are the project manager for your company and a new change request has been
approved for your project. This change request, however, has introduced several new risks
to the project. You have communicated these risk events and the project stakeholders
understand the possible effects these risks could have on your project. You elect to create a
mitigation response for the identified risk events. Where will you record the mitigation
response?