PrepAway - Latest Free Exam Questions & Answers

Author: admin

What document is Frank and the NHH Project team creating in this scenario?

Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document is Frank and the NHH Project team creating in this scenario?

What is a pure risk?

Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?

Which one of the following is the best explanation for completing qualitative risk analysis?

David is the project manager of HGF project for his company. David, the project team, and several key stakeholders have completed risk identification and are ready to move into qualitative risk analysis. Tracy, a project team member, does not understand why they need to complete qualitative risk analysis. Which one of the following is the best explanation for completing qualitative risk analysis?

What is the project’s cost performance index?

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete – though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project’s cost performance index?


Page 197 of 277« First...102030...195196197198199...210220230...Last »