what term?

A high-profile, high-priority project within your organization is being created. Management wants you to pay special attention to the project risks and do all that you can to ensure that all of the risks are identified early in the project. Management has to ensure that this project succeeds. Management’s risk aversion in this project is associated with what term?

Who is correct in this scenario?

Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?

When will the quantitative risk analysis process need to be repeated?

Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?


Page 181 of 277« First...102030...179180181182183...190200210...Last »