.Who is ultimately responsible for providing requirement specifications to the softwaredevelopment
team?
A.
The project sponsor
B.
The project members
C.
The project leader
D.
The project steering committee
Explanation:
The project sponsor is ultimately responsible for providing requirement specifications to the
software-development team.