Normally, it would be essential to involve which of the following stakeholders in the initiation stage
of a project?
A.
System owners
B.
System users
C.
System designers
D.
System builders
Explanation:
System owners are the information systems (project) sponsors or chief advocates. They normally are
responsible for initiating and funding projects to develop, operate and maintain information
systems. System users are the individuals who use or are affected by the information system.
Their requirements are crucial in the testing stage of a project. System designers translate business
requirements and constraints into technical solutions. System builders construct the system based
on the specifications from the systems designers. In most cases, the designers and builders are one
and the same.