Which of the following is an acceptable method for handling positive project risk? seenagape 11 years ago Which of the following is an acceptable method for handling positive project risk? A.Exploit B.Avoid C.Mitigate D.Transfer Explanation: Exploit is a method for handling positive project risk.not the positive risk. ← Previous question Next question →