What often results in project scope creep when function…

What often results in project scope creep when functional requirements are not defined as well as they could
be?

A.
Inadequate software baselining

B.
Insufficient strategic planning

C.
Inaccurate resource allocation

D.
Project delays

Explanation:
Inadequate software baselining often results in project scope creep because functional requirements are
not defined as well as they could be.