What is the immediate step after this monitoring process that has to be followed in response to risk

You are the project manager in your enterprise. You have identified occurrence of risk event in
your enterprise. You have pre-planned risk responses. You have monitored the risks that had
occurred. What is the immediate step after this monitoring process that has to be followed in
response to risk events?

A.
Initiate incident response

B.
Update the risk register

C.
Eliminate the risk completely

D.
Communicate lessons learned from risk events

Explanation:

When the risk events occur then following tasks have to done to react to it:
Maintain incident response plans
Monitor risk
Initiate incident response
Communicate lessons learned from risk events