The PRIMARY focus of the change control process is to e… seenagape 7 years ago The PRIMARY focus of the change control process is to ensure that changes are: A. authorized. B. applied. C. documented. D. tested. Explanation: changes are applied, documented and tested; however, they are not the primary focus. ← Previous question Next question →