When developing a disaster recovery plan, the criteria for determining the acceptable downtime should be the:
When developing a disaster recovery plan, the criteria for determining the acceptable downtime
should be the:
A lower recovery time objective (RTO) results in:
A lower recovery time objective (RTO) results in:
Regarding a disaster recovery plan, the role of an IS auditor should include:
Regarding a disaster recovery plan, the role of an IS auditor should include:
To find the root cause of this, the IS auditor should FIRST review the:
During a disaster recovery test, an IS auditor observes that the performance of the
disaster recovery site’s server is slow. To find the root cause of this, the IS auditor should FIRST
review the:
This implies that the system can tolerate:
An organization has a recovery time objective (RTO) equal to zero and a recovery point
objective (RPO) close to 1 minute for a critical system. This implies that the system can tolerate:
Which of the following issues should be the GREATEST concern to the IS auditor when reviewing an IT disaster r
Which of the following issues should be the GREATEST concern to the IS auditor when
reviewing an IT disaster recovery test?
which of the following is key to the continued effectiveness of a disaster recovery plan (DRP)?
The frequent updating of which of the following is key to the continued effectiveness of a
disaster recovery plan (DRP)?
The test has been successful, but gives only partial assurance that the:
A live test of a mutual agreement for IT system recovery has been carried out, including a
four-hour test of intensive usage by the business units. The test has been successful, but gives
only partial assurance that the:
To address an organization’s disaster recovery requirements, backup intervals should not exceed the:
To address an organization’s disaster recovery requirements, backup intervals should not exceed
the:
Which of the following would have the HIGHEST priority in a business continuity plan (BCP)?
Which of the following would have the HIGHEST priority in a business continuity plan (BCP)?