What is a reliable technique for estimating the scope and cost of a software-development project?

What is a reliable technique for estimating the scope and cost of a software-development project?

A. Function point analysis (FPA)

B. Feature point analysis (FPA)

C. GANTT

D. PERT

Explanation:

A function point analysis (FPA) is a reliable technique for estimating the scope and cost of a software-development project.