PrepAway - Latest Free Exam Questions & Answers

Category: CRISC

Exam CRISC: Certified in Risk and Information Systems Control

which item?

You are the project manager for BlueWell Inc. You have noticed that the risk level in your project
increases above the risk tolerance level of your enterprise. You have applied several risk
response. Now you have to update the risk register in accordance to risk response process. All of
the following are included in the risk register except for which item?

What risk response has been used here?

Ben is the project manager of the CMH Project for his organization. He has identified a risk that
has a low probability of happening, but the impact of the risk event could save the project and the
organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs
her to research the time, cost, and method to improve the probability of the positive risk event. Ben
then communicates the risk event and response to management. What risk response has been
used here?

Where will you record the mitigation response?

You are the project manager for your company and a new change request has been approved for
your project. This change request, however, has introduced several new risks to the project. You
have communicated these risk events and the project stakeholders understand the possible
effects these risks could have on your project. You elect to create a mitigation response for the
identified risk events. Where will you record the mitigation response?


Page 17 of 37« First...10...1516171819...30...Last »