what will be the Annual Loss Expectancy (ALE) of the project?
You are the project manager of the NHQ project in Bluewell Inc. The project has an asset valued
at $200,000 and is subjected to an exposure factor of 45 percent. If the annual rate of occurrence
of loss in this project is once a month, then what will be the Annual Loss Expectancy (ALE) of the
project?
Which of the following is NOT the method of Qualitative risk analysis?
Which of the following is NOT the method of Qualitative risk analysis?
which of the following processes are you working?
You work as a Project Manager for Company Inc. You are incorporating a risk response owner to
take the job for each agreed-to and funded risk response. On which of the following processes are
you working?
which of the following contract clauses?
To minimize costs and improve service levels an outsourcer should seek which of the following
contract clauses?
which of the following activities is MOST likely to lead to the introduction of weaknesses in security softwar
In a well-controlled environment, which of the following activities is MOST likely to lead to the
introduction of weaknesses in security software?
Which of the following is a performance measure that is used to evaluate the efficiency of an investment or to
Which of the following is a performance measure that is used to evaluate the efficiency of an
investment or to compare the efficiency of a number of different investments?
which of the following should be kept in the organization?
When an organization is outsourcing their information security function, which of the following
should be kept in the organization?
Which of the following is the BEST indicator that security awareness training has been effective?
Which of the following is the BEST indicator that security awareness training has been effective?
What must Alice do to move forward with her change request?
You are the program manager for your organization and you are working with Alice, a project
manager in her program. Alice calls you and insists you to add a change to program scope. You
agree for that the change. What must Alice do to move forward with her change request?