PrepAway - Latest Free Exam Questions & Answers

Author: seenagape

What change control system should the costs be entered into for review?

You are the project manager for your organization to install new workstations, servers, and cabling
throughout a new building, where your company will be moving into. The vendor for the project
informs you that the cost of the cabling has increased due to the some reason. This new cost will
cause the cost of your project to increase by nearly eight percent. What change control system

should the costs be entered into for review?

Which type of analysis you are performing?

You are the risk official at Bluewell Inc. There are some risks that are posing threat on your
enterprise. You are measuring exposure of those risk factors, which has the highest potential, by
examining the extent to which the uncertainty of each element affects the object under
consideration when all other uncertain elements are held at their baseline values. Which type of
analysis you are performing?


Page 617 of 751« First...102030...615616617618619...630640650...Last »