which of the following risk prioritization options would this case be categorized?

You are the project manager of RFT project. You have identified a risk that the enterprise’s IT
system and application landscape is so complex that, within a few years, extending capacity will
become difficult and maintaining software will become very expensive. To overcome this risk the
response adopted is re-architecture of the existing system and purchase of new integrated
system. In which of the following risk
prioritization options would this case be categorized?