Which two tasks should be performed when producing a project plan for a Service Availability and
Performance Management solution? (Choose two.)

A.
Create a work breakdown structure
B.
Schedule working group meetings for the project
C.
Develop a timeline based on a level of effort for each milestone
D.
Identify the team members that will be working on the solution
E.
Develop a system to identify milestones as the project progresses
Explanation: