Which two steps should be emphasized when gathering the technical deployment requirements from the s

Which two steps should be emphasized when gathering the technical deployment requirements
from the stakeholders so that a full technical architecture is documented and approved? (Choose
two.)

A.
determine the sources of data

B.
determine other external integration points

C.
verify the installation of an IBM Tivoli Netcool/OMNIbus ObjectServer instance

D.
verify the hard disk space requirements on the IBM Tivoli Netcool/lmpact Server

E.
verify that all the necessary operating system patches and packages are installed on the IBM
Tivoli Netcool/lmpact Server