IBM Exam Questions

which order does IBM Tivoli Workload Scheduler V8.6 analyze the variable tables when generating a pl

In which order does IBM Tivoli Workload Scheduler V8.6 analyze the variable tables when generating
a plan?

A.
1. Default variable table
2. Run Cycle
3. Job Stream
4. Workstation

B.
1. Default variable table
2. Job Stream
3. Workstation
4. Run Cycle

C.
1. Run Cycle
2. Job Stream
3. Workstation
4. Default variable table

D.
1. Job Stream
2. Run Cycle
3. Workstation
4. Default variable table