The YARN High Availability feature adds redundancy in the form of an Active/Standby. Which of the following
will pair to remove this otherwise single point of failure?

A.
JobTracker
B.
Data Node
C.
Management Node
D.
Resource Manager
Explanation:
http://hadoop.apache.org/docs/current/hadoop-yarn/hadoop-yarn-site/ResourceManagerHA.html