Which activity should be included during the requirements gathering phase for automating account pro

Which activity should be included during the requirements gathering phase for automating account provisioning?

A.
document reverse password synchronization

B.
document challenge and response questions

C.
document Self-Service Console requirements

D.
document relationships between roles and accounts