Which action will allow the administrator to restore the correct version of the library in the futur

A tape cycle consists of 5 daily save tapes. After restoring a library from the Monday tape the
administrator discovered that the library restored was from 2 weeks ago rather than last week.
Which action will allow the administrator to restore the correct version of the library in the future?

A.
Modify the save procedure to initialize the tape prior to the save.

B.
Use the OMITLIB parameter on the restore to omit the older versions of the library.

C.
Use sequence number *LAST on the restore to restore the most recent version of the library.

D.
Use the POSITION parameter on the restore to specify *LASTSAV restoring only the most
recent version.