What must be checked if the status of JOB2 on FTA2 shows HOLD?

Below is a job stream definition where conman status on fault-tolerant agent FTA1 shows that JOB1
is SUCC and both FTA’s are actively launching jobs.
SCHEDULE FTA2#LAB
:
FTA1#J0B1
FTA2#JOB2 Follows JOB1
END
What must be checked if the status of JOB2 on FTA2 shows HOLD?

A.
FTA1 job limit

B.
FTA1 fence limit

C.
batchman process on FTA1

D.
LINK status for FTA1 and FTA2