IBM Exam Questions

What is used to define temporal relationships between tasks that are logically related?

A user creates a plan for a project by using the Formal Project Management process
template. What is used to define temporal relationships between tasks that are logically

related?

A.
resource leveling

B.
schedule dependencies

C.
schedule constraints

D.
plan attributes