What is the minimum length of time that technical support will be offered for certain products
under the Enhance IBM Support Lifecycle policy?
A.
a minimum of 5 months after the publishing of a notice of support discontinuance End of
Support
B.
a minimum of 5 years beginning at the planned availability date of the version/release of the
product
C.
a minimum of 3 years beginning at the planned availability date of the version/release of the
product
D.
A minimum of 3 years beginning plus an additional 12 months only for customers who are
migrating to a supported version of the product