What is the key consideration for estimating the time to complete an IBM Tivoli Storage Manager (TSM

What is the key consideration for estimating the time to complete an IBM Tivoli Storage
Manager (TSM) upgrade migration?

A.
The number of TSM clients to be upgraded.

B.
The defined size of the source TSM database.

C.
The number of CPU cores allocated to the Butterfly Exporter.

D.
The resources available on the source and target TSM environments.