What are two prerequisites to an Optim archiving Project Kickoff meeting? (Choose two.)

A.
Obtain allOptim software required for project.
B.
Set up hardware for all environment installations.
C.
Review theOptim and application specific documentation.
D.
Finalize all archiving requirements.
E.
Choose the project sponsor.