What approach should the integration developer take while implementing this process?

An integration developer is planning to create a BPEL process to help with the management
of customer requests. The developer is intending to use a short-running process for the
implementation because it has been determined that the performance of the process is a
high priority, but the process must also be able to compensate for changes to the
customer’s request. What approach should the integration developer take while
implementing this process?

A.
Implement the short-running process as planned, but call the appropriate compensation
activity from a fault handler in the process.

B.
Implement the short-running process as planned, but associate an undo-operation with
the appropriate invoke activity in the process.

C.
Since compensation is not supported in short-running processes, implement a
long-running process using compensation pairs.

D.
Since compensation is not supported in short-running processes, use a compensation
handler and a compensation pair together in the log-running process