IBM Exam Questions

what action must occur before the planned WPAR can be successfully defined as a NIM client?

When preparing to install a System WPAR using NIM, what action must occur before the planned
WPAR can be successfully defined as a NIM client?

A.
Install AIX onto the global environment.

B.
Register the planned hostnames to DNS.

C.
Define the global environment LPAR as a NIM client.

D.
Create an lpp_source with the WPAR-specific backup files.

Explanation: