A design company has a process with 4 activities. The activity that occurs first is Submit
Design and it is implemented as a Human Service. The next two activities, Review Design
Engineering and Review Design Colors, occur in parallel, are always executed, and are
both implemented as a Subprocess. The final activity Approve Design, is implemented as a
Human Service and occurs after Review Design Engineering and Review Design Colors
have both been completed. Select the business process diagram that matches the
description of the company’s process.

A.
Exhibit C
B.
Exhibit D
C.
Exhibit B
D.
Exhibit A