Which settings control this behavior?
An administrator has a requirement to ensure that purchase requisitions have been approved before being able to create purchase orders from them. Which settings control this behavior? A. Clear the Allow PO Creation From Unapproved PR? checkbox in Purchasing Options. B. Clear the Allow PO Creation From Unapproved PR? checkbox on the purchase requisition. C. […]
A master PM can be used to do which of the following?
A master PM can be used to do which of the following? A. Create a job plan revision. B. Generate work orders for associated PMs. C. Create associated PMs for an item’s location. D. Change the status of work orders generated from associated PMs. Reference: http://www.redbooks.ibm.com/redbooks/pdfs/sg247761.pdf (page 55)
In which application can this be done?
A company has a requirement to have labor certificates defined. In which application can this be done? A. Crews B. People C. Certifications D. Qualifications
Which feature does this?
An engineer schedules a very complex asset report developed in BIRT. The engineer needs to set a feature to be able to retrieve the report contents from within Maximo for very large files that are restricted by the email server. Which feature does this? A. Direct Print B. Email with a File URL C. Email […]
What needs to be created?
A company has a requirement to share calendar, classification, job plan, item description and PM data. What needs to be created? A. Single organization, single site environment B. Multiple organizations with a shared site environment C. Multiple organizations with one site per organization environment D. Multiple organizations with multiple sites per organization environment
How can this be achieved?
A company has a requirement to have items in the storerooms to be reordered automatically. How can this be achieved? A. Reorder Escalation B. Reorder Cron Task C. Reorder – Reorder Items D. Reorder Direct Issue Items/Services
What other setting need to be selected in addition to the frequency value?
A fixed-schedule PM needs to be set up. What other setting need to be selected in addition to the frequency value? A. Alert Lead (DAYS) must equal 0 B. Alert Lead (DAYS) must be greater than 0 C. Use Last Work Order’s Start Date to Calculate Next Due Date? checked D. Use Last Work Order’s […]
With which statuses can this be accomplished?
A supervisor is required to report actual work hours by work order number. With which statuses can this be accomplished? (Choose two.) A. INPRG B. WAPPR C. CANCEL D. PNDREV E. COMPLETE
What type of role is used to assign the work order to the environmental inspector?
A custom field has been added to the Work Order Tracking application to identify the inspector for environmental impacts of each work order. What type of role is used to assign the work order to the environmental inspector? A. Person B. Person Group C. A set of data related to the record D. A set […]
What is the name of this feature?
The user wants to have a new job plan reference an existing job plan so that the data in the existing job plan will be available without re-entering it. What is the name of this feature? A. Nested job plans B. Job plan revisions C. Job plan sequences D. Attachment job plans