PrepAway - Latest Free Exam Questions & Answers

Category: C2010-571

Exam C2010-571: IBM Tivoli Process Automation Engine V7.5 Implementation

Which three data elements must be included to meet this requirement?

A company wants precedence relationships between work orders and tasks to automate the flow
of status changes between them. Specifically, it wants to establish some job plans to set finish-tostart relationships between the work orders and tasks so that successive work can be initiated as
soon as its predecessor is completed. Which three data elements must be included to meet this
requirement? (Choose three.)