What is a required step for a job Plan to be defined?
What is a required step for a job Plan to be defined?
which application can this be done?
The solution designer has been asked to create records for manufacturers, vendors, couriers, and
suppliers that will be used for procurement purposes to use assources for contractors. In which
application can this be done?
which level are Master Preventive Maintenance records defined?
At which level are Master Preventive Maintenance records defined?
Which application does this describe?
A company generates contracts for various work or purchases to replenish the stock in the
Storeroom. However, each time a new contract is drawn up, they have to send the contract off to
the legal department, which takes one to two days delaying the placing of a timely Purchase
Order. Instead, the company wants to centralize the terms and conditions that are used for each
company, and for these to be copied to each new
contract. Which application does this describe?
What does IBM Maximo Asset Management V7.1 call these steps or operations?
Each maintenance job can be broken down into a series of steps that must be performed to
complete the job. What does IBM Maximo Asset Management V7.1 call these steps or operations?
which option must be completed?
To apply the configuration changes made in the Logging application, which option must be
completed?
Which authentication process meets this requirement?
A customer wants to implement a security authentication process in IBM Maximo Asset
Management V7.1 which minimizes the number of Login IDs and passwords that a user must
rememeber. Which authentication process meets this requirement?
Which three attributes does Labor Reporting capture?
Which three attributes does Labor Reporting capture? (Choose three)
Which type of Portlet provides the solution?
A client has requested to see a graph on the Start Center that shows the count of all open Work
Orders. The graph should show the highest acceptable number before action is take, and the
highest number at which point or above some corrective measures must be taken. The three
indicators should be shown as green=ok, amber=warning, and red=action. Which type of Portlet
provides the solution?
which three options can an Item or Tool be charged?
To which three options can an Item or Tool be charged? (Choose three)