The following steps are used to create an agent in Event Studio. Which sequence logically orders
the items from first to last?Add a task Schedule the agent Specify an event condition Specify the
task execution rules
A.
1,2,3,4
B.
1,3,4,2
C.
3,1,4,2
D.
3,4,1,2
Explanation:
Answer is C :3,1,4,2
Specify an event condition
Add a task
Specify the task execution rules
Schedule the agent