In the design and build phase, which statement describes an end-to-end systems connectivity or “shake-out” test?

A.
Build the first full iteration of the project required Access Definition; build and associate to a named Request; run the request.
B.
Log in to theOptim Configuration tool; create the Optim Directory; initialize and Enable Security.
C.
Test workstation and server connectivity to theOptim directory and to all DB Aliases; configure a basic Access Definition; run a local request; restore/insert/load data as applicable.
D.
Build one of each type ofOptim definition and associated requests; run each from both the workstation, and server.