Which statement is true about a relationship and a dependency between major project plan
milestones?

A.
Pain points must be documented before defining the business processes.
B.
Authentication requirements must be understood before the system is designed.
C.
The Service Availability and Performance Management (SAPM) software installation is a
prerequisite for software configuration.
D.
Existing SAPM tools must be either configured or decommissioned before new SAPM tools are
installed.