Which of the following costs of quality is a failure cost?
A. Systems development costs.
B. Costs of inspecting in-process items.
C. Contract penalty for delivery of nonconforming goods.
D. Costs of quality circles.
Explanation:
Failure costs are incurred after defective output has been removed from production. A contract penalty for faulty goods is an example of an external failure cost.