When creating a resource plan within a demand, how are the default dates on a resource plan determin

When creating a resource plan within a demand, how are the default dates on a resource plan determined?

A. From demand start date and due date

B. Resource plan(s) cannot be created from demand

C. Using demand created date

D. From portfolio date