Under which heading in the POTI model should the current performance level of an operational area be recorded?
A. Process
B. Organization
C. Technology
D. Information
Reference: https://pmtips.net/article/poti-model-programme-blueprints
Under which heading in the POTI model should the current performance level of an operational area be recorded?
A. Process
B. Organization
C. Technology
D. Information
Reference: https://pmtips.net/article/poti-model-programme-blueprints