Under which heading in the POTI model should the current performance level of an operational area be recorded?

Under which heading in the POTI model should the current performance level of an operational area be recorded?

A. Process

B. Organization

C. Technology

D. Information

Reference: https://pmtips.net/article/poti-model-programme-blueprints