Which is NOT a purpose of a Blueprint?
Which is NOT a purpose of a Blueprint? A. Provide a basis for modelling benefits B. Provide a usable basis for designing the Projects Dossier C. Ensure coherence of the entire future state D. Describe how to get to the future state Reference: https://www.axelos.com/news/blogs/may-2017/the-blueprint-a-cornerstone-of-programmes-and-msp
Which is a characteristic of a programme?
Which is a characteristic of a programme? A. It manages the planning, monitoring and control of projects B. It co-ordinates, directs and oversees the implementation of a set of related projects and activities C. It delivers one or more outputs in accordance with an agreed business case D. It defines an organization’s approach to achieving […]
Which risk response encourages collaboration on risk management activities?
Which risk response encourages collaboration on risk management activities? A. Avoid B. Reduce C. Share D. Prepare contingent plans Reference: https://www.simplilearn.com/overview-of-risk-and-issue-management-tutorial
Which document should be used to provide guidance on the standards that should be followed when producing outp
Which document should be used to provide guidance on the standards that should be followed when producing outputs? A. Projects Dossier B. Project Brief C. Programme Blueprint D. Programme Brief Reference: https://www.simplilearn.com/overview-of-planning-and-control-tutorial
Which is a description of a programme resource?
Which is a description of a programme resource? A. The objective of a programme B. A process to control a programme C. A logical grouping of projects within a programme D. An input required by a programme
Which is a feature of an effective programme organization?
Which is a feature of an effective programme organization? A. Clear accountability for each management role B. A business case agreed by the stakeholders C. Monitored and controlled programme changes D. A quality assured configuration management system
Under which heading in the POTI model should the current performance level of an operational area be recorded?
Under which heading in the POTI model should the current performance level of an operational area be recorded? A. Process B. Organization C. Technology D. Information Reference: https://pmtips.net/article/poti-model-programme-blueprints
Which role is responsible for creating and communicating the vision for the programme?
Which role is responsible for creating and communicating the vision for the programme? A. Programme office B. Business change manager C. Programme manager D. Senior responsible owner Reference: https://www.axelos.com/news/blogs/january-2021/msp-vision-statement-programmes-with-purpose
Which of the following policies is suitable for increasing the number of instances in an AS group at a fixed t
Which of the following policies is suitable for increasing the number of instances in an AS group at a fixed time each week? A. Alarm B. Scheduled C. Periodic D. All of above Reference: https://support.huawei.com/enterprise/en/doc/EDOC1100062374/71864455/as-group
After an AS group is deleted, ECS instances automatically created by AS will also be deleted.
After an AS group is deleted, ECS instances automatically created by AS will also be deleted. A. True B. False Reference: https://support.huaweicloud.com/intl/en-us/as_faq/faq_440.html