Which task is performed by the Change Authority?

Which task is performed by the Change Authority?

A.
Set a change budget

B.
Approve or reject a request for change within approved limits

C.
Refer changes that exceed budgetary limits to the Project Manager for approval

D.
Update the configuration management system when a change is approved