Which statement about the prioritize practice is true?

A.
A segmented portfolio should use the same criteria to prioritize each segment
B.
Mandatory projects should not be included in the normal prioritization process
C.
Prioritization of initiatives should be based on an estimate of financial benefits that may be
achieved
D.
A mandatory requirement should be reviewed to ensure that the planned change is cost
effective
Explanation: