Which products, identified when creating a product breakdown structure, should each have a
corresponding entry in the Risk Register?
A.
Those that have been completed, but have NOT been quality checked
B.
Those that have been broken down into sub-products
C.
Those to be created outside the scope of the project
D.
Those dependent on more than one other product