Which product summarizes progress and is used to decide whether to amend the project scope or stop t

Which product summarizes progress and is used to decide whether to amend the project scope or
stop the project?

A.
Checkpoint Report

B.
End Stage Report

C.
End Project Report

D.
Product Status Account