which product is updated to incorporate the estimated time and costs from the Project Plan?

During the Initiating a Project process, which product is updated to incorporate the estimated time
and costs from the Project Plan?

A.
Project Product Description

B.
Business Case

C.
Project Brief

D.
Project mandate

Explanation: