which product is updated to incorporate the estimated time and costs from the Project Plan? seenagape 10 years ago During the Initiating a Project process, which product is updated to incorporate the estimated timeand costs from the Project Plan? A. Project Product Description B. Business Case C. Project Brief D. Project mandate Explanation: ← Previous question Next question →