Which of these would fall outside the scope of a typical service change management process?

A.
A change to a contract with a supplier
B.
A firmware upgrade to a server that is only used for IT Service Continuity purposes
C.
An urgent need to replace a CPU to restore a service during an incident
D.
A change to a business process that depends on IT Services
Explanation: